July Update - Week 15
Finally we have two of the necessary services to site: electricity and water. We were instructed to dig a 50m trench by Western Power from a pylon in the adjacent field, right up to the barn. The cable was “moled” under the county highway by an external contractor who laid the cable in the trench ready for the August live connection.
In anticipation of the welsh wet weather approaching a storm drain was constructed to cope with flash flooding from the hills above us which will collect behind the retaining wall.