January Update - Week 40With the underfloor heating in place and tested we could get on with laying the floor screed, the final layer before the floor tiles.
It took most of the week to finish the whole floor as we chose not to get a pour but instead Dave must have mixed over 100 barrow-fulls of screed.
The other picture details the roof trusses from below